Baufortschritt Oktober 2024

Baustellenfotos Oktober 2024

Auszüge aus den Nachrichten der Schule im Oktober 2024

07.10.2024

Good morning Simone.
The contractor is very fast and they are doing good work.
They are through with footing as you can see.
Greetings from chihame1 people.
Regards, John

17.10.2024

Hello Simone.
The work  is really  progressing well. The community  is really  Thank full with  the  work. Attach is the photo of the work.“

24.10.2024

Hello Simone.
Good afternoon.
I want to update on the progress of the project. It is still progressing well. Know  they are at above  ringbeam.see the photo

29.10.2024

Good  afternoon.
Update  of the project. They are through  with  the  walls building. Now  they  are waiting  for roofing and they are constructing a toilet. attached  are the of walls